Bogey Hills Country Club: St. Charles, MO

PROJECT DESCRIPTION

Client: Bogey Hills Country Club
Project:  
New Construction Clubhouse
General Contractor:  
Brinkmann Constructors
Architect:  TRi Architects
Floor Area:
40,000 sf 
Construction Schedule: 
May 2018

ROLE

Engineer of Record
Installing Mechanical Contractor

PROJECT APPROACH

Design/Build

 PROJECT SCOPE


In February 2017, the 55-year-old Bogey Hills Country Club in St. Charles, MO was destroyed in a massive fire.  Wiegmann was chosen as Engineer of Record and Installing Mechanical Contractor for the construction of the new two-story clubhouse.

PROJECT CHALLENGE/SOLUTION


Wiegmann engineered a new energy-efficient and cost-effective HVAC system. A combination of multi-zone variable air volume (VAV) and single zone variable air volume packaged rooftop units were designed to minimize fan speed and fan energy consumption when possible.  Wiegmann also designed and installed a DDC control system to optimize energy savings and provide the owner the benefit of remote monitoring/scheduling.