    PROJECT DESCRIPTION

    Client: 
    Quality Custom Distribution: Apopka, Florida
    Project: 
    New Construction Refrigerated Food Warehouse
    General Contractor:
    ARCO Beverage Group
    Floor Area: 
    180,000 sf
    Construction Schedule: 
    Eleven months, Fall 2017

    PROJECT APPROACH

    Design/Build

    ROLE

    HVAC, Refrigeration and Controls Design/Build Contractor

    PROJECT SCOPE

    The project included the design and installation of HVAC, refrigeration and automation systems for a newly constructed 180,000 food warehouse, including 14,450 square feet of main office and warehouse office areas; 87,000 square feet of warehouse space; and 81,000 square feet of refrigerated warehouse spaces including a cold dock, cooler, meat cooler, tomato room and freezer. We also installed automation controls for the evaporators and rooftop condenser units.

     PROJECT CHALLENGE/SOLUTION

    Wiegmann designed and installed the HVAC and refrigeration systems for the 180,000-square- foot food warehouse on a fast-track timeline, completing in just eleven months.

    ENERGY SAVINGS

    To conserve energy, Wiegmann installed electronic expansion valves on refrigeration equipment in lieu of mechanical valves, and added VFDs to the condenser fan motors.